Friday, September 10, 2010

Sanitary service repairs/installations and water services continue this week and into next week. Each resident will be notified on the day of the work when the water will need to be shut down for a short amount of time. The contractor is scheduled to start pavement removal and curb and gutter removal late next week. The contractor will be utilizing aggregate to provide access to residential driveways at the end of each work day.

No comments:

Post a Comment