Friday, June 25, 2010

The contractor may be onsite next week to grind the pavement over the proposed water main trench location. (see post below), but we do not have a definite schedule yet. Check back next week!

Friday, June 18, 2010

The contractor, PirTano Construction Company, plans to begin layout of the water main next week. They are going to take a grinding machine and grind the pavement right where the water main is going to be installed. By doing this, we will be leaving a large portion of the road intact during the water main installation. The contractor does not plan to do any digging until after July 4th.

Friday, June 4, 2010

Work is still scheduled to begin mid-June.