Friday, October 1, 2010

The contractor is scheduled to finish the sanitary service repairs/installations and water services on Barbary Lane and continue the remaining storm sewer work next week. The contractor is scheduled to continue with preparing/grading the aggregate base course into next week. The contractor is scheduled to start curb and gutter replacement on Carousel next week. Residents will need to park on the street for 4 or 5 days while the concrete curb and gutter cures in front of their driveways. The contractor will notify residents that need to have their vehicles moved out of their driveways prior to concrete work.

Friday, September 24, 2010

The contractor is scheduled to finish the sanitary service repairs/installations, water services and the remaining storm sewer work late next week. The contractor is scheduled to continue with preparing/grading the aggregate base course this week and into next week. The contractor is scheduled to start curb and gutter replacement at the west half of Carousel next week. Residents will need to park on the street for 4 or 5 days while the concrete curb and gutter cures in front of their driveways. The contractor will notify residents that need to have their vehicles moved out of their driveways prior to concrete work.

Friday, September 17, 2010

The contractor is scheduled to finish the sanitary service repairs/installations and water services next week. Pirtano Construction is scheduled to begin removing the existing asphalt pavement and curb, weather permitting, this Friday, September 17th. The pavement area to be removed will be from the west end of Carousel at Crestwood to east of Briarford. It is imperative that no vehicles be parked on the streets in this section between 7AM and 5 PM. The roads will still remain open to traffic; however, there will be short periods of time when the road or your driveway will be blocked while trucks are being loaded. Pirtano will insure that access to your driveway is possible by installing temporary stone ramps by the end of each day.

Friday, September 10, 2010

Sanitary service repairs/installations and water services continue this week and into next week. Each resident will be notified on the day of the work when the water will need to be shut down for a short amount of time. The contractor is scheduled to start pavement removal and curb and gutter removal late next week. The contractor will be utilizing aggregate to provide access to residential driveways at the end of each work day.

Thursday, September 2, 2010

Sanitary service repairs/installations continue this week. The water services will start soon. As noted below, each resident will be notified on the day of the work when the water will need to be shut down for a short amount of time.

Friday, August 27, 2010

The water main installation is complete, filling and pressure testing has been done and the new main is being chlorinated and tested. Test results should be in Tuesday and then the contractor will begin water service installations to each home. On the day the contractor works on your service they will knock on the door to notify residents of the water shutoff. At the same time, the contractor is doing sewer repairs across the roads which necessitate road closures at that location.

Friday, August 20, 2010

Water main installation is nearing completion. Once everything is installed, the contractor will perform a pressure test. For the test, the main is filled with water and pressurized to 150 pounds per square inch (psi). To pass the pressure test, pressure must be held at 150 psi for 2 hours. Once the pressure test passes, the water main gets chlorinated. Once the chlorination tests pass, the contractor can begin on water services. Contractor is going to start on storm sewers while waiting for the water main testing.