Monday, December 6, 2010

Work is substantially complete with the exception of punch list work.

Tuesday, November 30, 2010

Work is substantially complete with the exception of punch list work.

Monday, November 22, 2010

Work is substantially complete with the exception of punch list work.

Wednesday, November 10, 2010

The contractor has paved the final lift of asphalt (surface course) this week. The contractor will continue with parkway restoration (sodding) this week. Upon completion of the sodding, the contractor will be completing punch list work.

Friday, November 5, 2010

The contractor will continue with parkway restoration (topsoil and sod) into next week. The contractor is scheduled to pave the final lift of asphalt (surface course) starting Monday morning.

Monday, November 1, 2010

The contractor is scheduled to pave the first lift of hot-mix asphalt (binder course) Tuesday and Wednesday of this week. After the binder course is paved, the contractor will work on parkway restoration and topsoil placement. The final lift of asphalt (surface course) is scheduled (weather permitting) for possibly Friday or early next week.

Thursday, October 28, 2010

UPDATE!

Hot-mix asphalt binder course will not be paved this Friday. Hot-mix asphalt binder course is scheduled for early next week.

Friday, October 22, 2010

The contractor will be finishing the remaining driveways on the south side of Carousel, both sides of Barbary, and the west side of Briarford this week. Weather permitting the contractor will be on site Saturday at 8 AM. Residents will need to park on the street for 4 or 5 days while the concrete curb and gutter and driveways cure. Next week, the contractor is scheduled to prepare for the paving of the first lift of hot-mix asphalt (binder course).

Friday, October 15, 2010

The curb and gutter on the north side of Carousel is complete. The Contractor is scheduled to finish replacing driveway aprons by early next week on the north side of Carousel where the curb has been completed. Next week, the contractor is scheduled to work on the remaining curb and gutter (on the south side of Carousel, both sides of Barbary, and the west side of Briarford). Residents will need to park on the street for 4 or 5 days while the concrete curb and gutter cures in front of their driveways. The contractor will notify residents that need to have their vehicles moved out of their driveways prior to concrete work.

Friday, October 8, 2010

The contractor has completed the utility work for the project. The contractor is scheduled to place curb and gutter on Carousel (north side of road) this Friday, October 8, 2010 (weather permitting). Next week the contractor will work on driveway replacement (on the north side of Carousel) and continue fine grading the aggregate base course and prepare for curb and gutter installation on the south side of Carousel. Residents will need to park on the street for 4 or 5 days while the concrete curb and gutter cures in front of their driveways. The contractor will notify residents that need to have their vehicles moved out of their driveways prior to concrete work.

Friday, October 1, 2010

The contractor is scheduled to finish the sanitary service repairs/installations and water services on Barbary Lane and continue the remaining storm sewer work next week. The contractor is scheduled to continue with preparing/grading the aggregate base course into next week. The contractor is scheduled to start curb and gutter replacement on Carousel next week. Residents will need to park on the street for 4 or 5 days while the concrete curb and gutter cures in front of their driveways. The contractor will notify residents that need to have their vehicles moved out of their driveways prior to concrete work.

Friday, September 24, 2010

The contractor is scheduled to finish the sanitary service repairs/installations, water services and the remaining storm sewer work late next week. The contractor is scheduled to continue with preparing/grading the aggregate base course this week and into next week. The contractor is scheduled to start curb and gutter replacement at the west half of Carousel next week. Residents will need to park on the street for 4 or 5 days while the concrete curb and gutter cures in front of their driveways. The contractor will notify residents that need to have their vehicles moved out of their driveways prior to concrete work.

Friday, September 17, 2010

The contractor is scheduled to finish the sanitary service repairs/installations and water services next week. Pirtano Construction is scheduled to begin removing the existing asphalt pavement and curb, weather permitting, this Friday, September 17th. The pavement area to be removed will be from the west end of Carousel at Crestwood to east of Briarford. It is imperative that no vehicles be parked on the streets in this section between 7AM and 5 PM. The roads will still remain open to traffic; however, there will be short periods of time when the road or your driveway will be blocked while trucks are being loaded. Pirtano will insure that access to your driveway is possible by installing temporary stone ramps by the end of each day.

Friday, September 10, 2010

Sanitary service repairs/installations and water services continue this week and into next week. Each resident will be notified on the day of the work when the water will need to be shut down for a short amount of time. The contractor is scheduled to start pavement removal and curb and gutter removal late next week. The contractor will be utilizing aggregate to provide access to residential driveways at the end of each work day.

Thursday, September 2, 2010

Sanitary service repairs/installations continue this week. The water services will start soon. As noted below, each resident will be notified on the day of the work when the water will need to be shut down for a short amount of time.

Friday, August 27, 2010

The water main installation is complete, filling and pressure testing has been done and the new main is being chlorinated and tested. Test results should be in Tuesday and then the contractor will begin water service installations to each home. On the day the contractor works on your service they will knock on the door to notify residents of the water shutoff. At the same time, the contractor is doing sewer repairs across the roads which necessitate road closures at that location.

Friday, August 20, 2010

Water main installation is nearing completion. Once everything is installed, the contractor will perform a pressure test. For the test, the main is filled with water and pressurized to 150 pounds per square inch (psi). To pass the pressure test, pressure must be held at 150 psi for 2 hours. Once the pressure test passes, the water main gets chlorinated. Once the chlorination tests pass, the contractor can begin on water services. Contractor is going to start on storm sewers while waiting for the water main testing.

Friday, August 13, 2010

Water main installation continues along Carousel.

Saturday, August 7, 2010

The contractor is continuing with water main installation, including installing new fire hydrants.

Friday, July 30, 2010

The contractor began installing Plastic Watermain Pipe on Monday. This process will take several weeks.