Friday, September 24, 2010
The contractor is scheduled to finish the sanitary service repairs/installations, water services and the remaining storm sewer work late next week. The contractor is scheduled to continue with preparing/grading the aggregate base course this week and into next week. The contractor is scheduled to start curb and gutter replacement at the west half of Carousel next week. Residents will need to park on the street for 4 or 5 days while the concrete curb and gutter cures in front of their driveways. The contractor will notify residents that need to have their vehicles moved out of their driveways prior to concrete work.
Friday, September 17, 2010
The contractor is scheduled to finish the sanitary service repairs/installations and water services next week. Pirtano Construction is scheduled to begin removing the existing asphalt pavement and curb, weather permitting, this Friday, September 17th. The pavement area to be removed will be from the west end of Carousel at Crestwood to east of Briarford. It is imperative that no vehicles be parked on the streets in this section between 7AM and 5 PM. The roads will still remain open to traffic; however, there will be short periods of time when the road or your driveway will be blocked while trucks are being loaded. Pirtano will insure that access to your driveway is possible by installing temporary stone ramps by the end of each day.
Friday, September 10, 2010
Sanitary service repairs/installations and water services continue this week and into next week. Each resident will be notified on the day of the work when the water will need to be shut down for a short amount of time. The contractor is scheduled to start pavement removal and curb and gutter removal late next week. The contractor will be utilizing aggregate to provide access to residential driveways at the end of each work day.
Subscribe to:
Posts (Atom)